hi guys just posting costings thati had done up for me to self build for two storey 2100 house.
substructure
hardcore, excavation concrete, steel, radon barrier and floor screed -- 19,563.00
external wall
lintels, external plastering, insulation --- 25,273.96
internal walls
internal block work, lintels, flue liners, plaster and paint internally, timber stud partitions and plasterboard finish to 1st floor.--- 13,404.88
windows and doors externally
u.pvc windows and doors externally, windowboards.. -- 12,237.00
first floor
suspended slab skim finish and insulation --- 12,500.00
roof
cut roof, concrete tile finish, upvc fascia soffit ---20,482.00
plumbing
boiler, rads, oil tank sanitary ---- 20,000.00
electrial
lighting and sockets---5,350.00
2nd fix carpentery
door skirting--- 18,213.00
kitchen--- 10,000.00
tiling--- 4,000.00
floor finishes--- 12,000.00
Site works
septic tank and treatment area, concrete kerbing, percolation area--- 23,678.65
total--196,702.49
Vat-- 26,554.84
total inc Vat-- 223,257.33