J
Hi All,
I am in the process of having plans for a single story extension completed by my architect.
However i was thinking to avoid any 'extras' being added to the work by whatever builder we hire & to ensure the project is costed correctly I was planning on using a quantity surveyor to help us on this front, so basically my questions are:
is it necessary to have a QS for an extension or should the architect be sufficient?
Can a QS work with an Architect?
How much should i expect to pay a QS in Dublin?
thanks!
Alternatively you could also go to 2 or 3 builders and get them to price the job and itemise the works that they have included for and to make suitable allowances for unforseen items.
Compare the quotations and you should be able to see that they are all pricing the same works.
Your architect should also be able to compare these when they come back. This should save you some money.
a QS will only allow for provisional sums to cover unforeseen works and your prov sums may double depending on what they hit.
If a bill of Quantities is produced it will contain the contractors rates for items such as excavating rock, filling to soft spots, excavating around or parallel to existing services etc.
If items like these occur during construction in larger quantities than what is measured in the BoQ then yes it will cost you more but on the other hand the rate in the BoQ will apply to any additional works required which will prevent you from getting screwed by the contractor.
We always, 99% of the time
To avoid your contractor going bust with your money make sure you appoint your Architect to check his valuations for the works, hold a retention, 5%, and always pay in arrears.
Home truths.
No builder will work off a QS's spec.
Not advisible to use a QS for a house build.
There is no such thing as a fixed price contract.
Do not let your architect pick your builder.
No project manager or architects will spot all the mistakes.
You will pay for those mistakes regardless of QS's specs
You will pay extra charges no matter what you do.
Fraid that is the way it is.
How is this going to avoid your contractor going bust? It may ensure that you have not overpaid your contractor. But again Architects are not trained in cost Quantity Surveyors are hence the benefit of using a Quantity Surveyor.
Charlie honest question. How did ye get the job initially? Do you employ a QS?
No we employed a bid manager who worked with the project team who packaged up the drawings and spec for the works and sent them out to a variety of sub-contractors for pricing. Some packages to single source suppliers and some to multiple sources to compare prices.
I would be amazed if the architect was agreeing variations/progress claims off his own experience. He has the PQS there to advise on cost and he would act based on thier reports. The arch would not have an clue how a bill is prepared or the method of measurment.
We don't have bills of quants, it is a traditional contract that based on a specification of works and the drawings issued at tender stage forming the basis of the contract.
He wouldnt know how claims and variations are built up or what entitlments are allowed.
The Architect alters the drawings, he does so without consulting the PQS, we submit a variation CCF(contract change form) with cost and programme implications an agree in principal with the Architect whether it is a design change or design development.
We then submit a price to him detailing the works that are required as per his new design. He at the same time asks his PQS to price the variation as detailed on his drawing and compares our cost to his to see if he is getting value for money.
I think if you talk to an Architect you may find that they are far more astute and commercially aware than people on this thread are giving them credit for.
The arch is the contract administrator but he has a whole design team to advise him.
You are correct, he does have the design team to advise him however he is soley responsible for administering the contract and ultimately if it goes to court has to justify his decision and the basis that he made that on.
The Architect decides on whether payment is due or not for variations or alterations as he can argue whether it was a development of the design to make it work or a change to design.
As for your comment about retention im afraid it is incorrect. You should never have paid up front for any work so you should always have value for money. In fact you should have up to 2 months work on each payment if you factor in the time taken to process an application, issue a cert and recieve payment.
Your retention is taken from the amount you owe the builder in order to ensure at the end of the contract he makes good defects. I never said to pay up front for works. My coment was,
To avoid your contractor going bust with your money make sure you appoint your Architect to check his valuations(Builders valuation of work carried out) for the works, hold a retention, 5%, and always pay in arrears.
There is a far bigger risk to the builder with the client going bust and having 2 months 'Work in Progress'
The builder, if he fears this should have the money put in an escrow account in case of the client going bust.
If Architects have no training in cost, can you advise as why an Architect who is also the Contract Administrator, signs off the costs on my current scheme, currently on Phase 2 of 3, with a value c£46million, argues costs with us the main contractor for variations and instructs the PQS what to pay based on his assesments and dealings with us.
The PQS does not make payments, they make recommendations to the Architect. The Architect then issues a certificate based on the PQS recommendation to the client which pay the amount on the Cert.
What from of contract do you work under?
Joejoe
We use cookies and similar technologies for the following purposes:
Do you accept cookies and these technologies?
We use cookies and similar technologies for the following purposes:
Do you accept cookies and these technologies?