'Inexperience and Incompetence of the Builder', the Engineer had to come out on site an extra 8 times totalling 16 site visits instead of the original 8 that was agreed . The original bill was 3000 Plus vat now its 4,000 Plus Vat .
Again you need to find out why, why the lack of communication?Previous to this contact i did not hear anything from the Engineer saying that there was an issue or that they had to visit the site due to issues with the builder .
Why have you not requested the MOM or more to the point why has your architect not sent you the MOM, or kept you informed?I contacted the Architect about this and he said that the Engineer had attended the site about 16 times as the engineer was shown on the Site meetings as attending.
The MOM should clarify this, but you also need the Engineer to clarify their reasons for the extra site visits. You may need a response from your Contractor on this too!I contacted the Builder and he said that she contributed nothing to any site meeting and never said a word and often commented that there was no reason for him to be on site . So i dont know where this is coming from.
If the engineer had genuine concerns about the "Inexperience and Incompetence of the Builder", surely she should have raised these concerns with the client at the time?
In Op's case, there is clearly a gap in the information being furnished. Now, either the engineer is a complete shyster OR OP was not keeping an eye on the ball, or, more likely, knew about the extra visits , but reckoned if no-one told him, he would not pay. Not reckoning on the Cert not being provided.
The Jury is out, without all the facts, but I know where I'd put my money.
If the engineer had genuine concerns about the "Inexperience and Incompetence of the Builder", surely she should have raised these concerns with the client at the time?
The attendances by the engineer suggest an eight-week delay assuming one meeting a week and at least a month even if the meetings were twice weekly.
A month or two is a lot on a tight programme - did nobody notice programme dates slipping?
It really depends on the channels of communciation agreed at the start of the project. The Engineer may have raised these concerns to the Architect or indeed they could be covered in the MOM. As pointed out above, more often than not the Architect may be acting as the Project Manager on the project and all communciation from the design team members and the builder is done through the Project Manager. However the Client (OP) needs to clarify this?
Again, even if this was the case, shouldn't there be some formal written/email communication from the engineer to somebody noting the need for extra visits?OP was not keeping an eye on the ball, or, more likely, knew about the extra visits , but reckoned if no-one told him, he would not pay.
Would the minutes be the appropriate medium for communicating the need for extra visits?With a small design team and a contractor there should have been
- THREE supposedly competent and experienced people feeding comment to the client/employer.
- PLUS there should have been a regular set of Meeting Minutes circulated.
- PLUS the client should have made his own attendances and seen *some* sign of the problems.
Shouldn't he have done this justification BEFORE the extra visits, and not after?(i) The Engineer needs to give a full and detailed response for his reasons for each of the 8 site visits & justify his additional fees in doing so.
OK, but either way, there should be some communication from the engineer to somebody, before the extra visits were required, pointing the problems arising and the likely cost impacts. Surely that simple degree of change control would be standard practice for any professional?
Again, even if this was the case, shouldn't there be some formal written/email communication from the engineer to somebody noting the need for extra visits?
Would the minutes be the appropriate medium for communicating the need for extra visits?
Shouldn't he have done this justification BEFORE the extra visits, and not after?
OK, but either way, there should be some communication from the engineer to somebody, before the extra visits were required, pointing the problems arising and the likely cost impacts. Surely that simple degree of change control would be standard practice for any professional?
Again, even if this was the case, shouldn't there be some formal written/email communication from the engineer to somebody noting the need for extra visits?
Would the minutes be the appropriate medium for communicating the need for extra visits?
Shouldn't he have done this justification BEFORE the extra visits, and not after?
We use cookies and similar technologies for the following purposes:
Do you accept cookies and these technologies?
We use cookies and similar technologies for the following purposes:
Do you accept cookies and these technologies?