Hi All, building a new house ,due to some Structural Queries Architect requested that i get an Engineer ,Contract with Engineer(friend of Architect) agreed for doing up some Engineering drawings for Builder and 8 site visits for €3000 Euro Incl Vat, grand no problem .
Six months later i receive a letter from Engineer saying that due to the and i Quote 'Inexperience and Incompetence of the Builder', the Engineer had to come out on site an extra 8 times totalling 16 site visits instead of the original 8 that was agreed . The original bill was 3000 Plus vat now its 4,000 Plus Vat .
Previous to this contact i did not hear anything from the Engineer saying that there was an issue or that they had to visit the site due to issues with the builder .
I contacted the Architect about this and he said that the Engineer had attended the site about 16 times as the engineer was shown on the Site meetings as attending. I contacted the Builder and he said that she contributed nothing to any site meeting and never said a word and often commented that there was no reason for him to be on site . So i dont know where this is coming from .
I wrote back to the Engineer enclosing the remaining amount due on the original 3000 euro Figure + vat , but said that the extra 8 visits were not part of the original agreement and that I was not informed by the Engineer that there were issues requiring the Engineer to visit the site more often than agreed. I asked the Engineer to forward on the Engineer Certificate so that build could be passed.
The other day I received a letter back from the Engineer saying that i will not receive the Certificate until the extra 1000 plus vat was paid. I believe i am within my rights not to pay the extra 1000 Euros as the Engineer took it upon himself to come on site an extra 8 times without consulting me first. Looks like i will have to go the legal route but am i correct in my assumption that the engineer should not have made an extra 8 visits without consulting me and i am within my rights to demand the Certificate.
Regards, Jumper
Six months later i receive a letter from Engineer saying that due to the and i Quote 'Inexperience and Incompetence of the Builder', the Engineer had to come out on site an extra 8 times totalling 16 site visits instead of the original 8 that was agreed . The original bill was 3000 Plus vat now its 4,000 Plus Vat .
Previous to this contact i did not hear anything from the Engineer saying that there was an issue or that they had to visit the site due to issues with the builder .
I contacted the Architect about this and he said that the Engineer had attended the site about 16 times as the engineer was shown on the Site meetings as attending. I contacted the Builder and he said that she contributed nothing to any site meeting and never said a word and often commented that there was no reason for him to be on site . So i dont know where this is coming from .
I wrote back to the Engineer enclosing the remaining amount due on the original 3000 euro Figure + vat , but said that the extra 8 visits were not part of the original agreement and that I was not informed by the Engineer that there were issues requiring the Engineer to visit the site more often than agreed. I asked the Engineer to forward on the Engineer Certificate so that build could be passed.
The other day I received a letter back from the Engineer saying that i will not receive the Certificate until the extra 1000 plus vat was paid. I believe i am within my rights not to pay the extra 1000 Euros as the Engineer took it upon himself to come on site an extra 8 times without consulting me first. Looks like i will have to go the legal route but am i correct in my assumption that the engineer should not have made an extra 8 visits without consulting me and i am within my rights to demand the Certificate.
Regards, Jumper