Hi, I think that a percentage fee is unreasonable because if for instance someone wants to use particularly expensive materials this will push up the construction costs but will not affect the complexity of the build or increase the input from an the architect. I fully agree with ONQ's sentiments on what some people may perceive as being 'good value' is in fact exploitation but that works both ways. Is not a percentage fee a way of exploiting a situation where clients building an expensive house are seen as being able to afford to pay a professional more than he would have received were the house the same design but using less expensive materials? All professions and trades people and workers are suffering at the moment and out of necessity 'the client' will be looking for value for money ... which may indeed result in exploitation. Have we all not been living in cloud cuckoo land for the past 10 years???
Your question is sound and deserve an answer Brigid.
The short answer is "no" .
Percentage fees are not a means of exploiting clients.
This assumption arises from a lack of knowledge of how projects progress.
That's not so much an "I know more than you do" answer as a "here are some things you should know" comment.
So, without further ado, here are some things you should know.
---------------------------------------
1. Percentage fees are not charged pro-rata as cost increases.
Usually the percentage diminishes as the total cost rises.
My experience of clients suggests that those willing to spend the higher sums on their buildings expect a higher level of attendances - which have to be paid for.
---------------------------------------
2. The old "bumping up the materials bill" comment is seldom true where most buildings are concerned.
Primarily this is because most architects I know of do no build using extravagent materials - how many all copper clad or granite stone outer leaf houses do you know of?
Besides, the costs of materials alone do not form a significant cost of most buildings.
Costs are usually diviided thusly; -
1/3 Structure
1/3 Services
1/3 Fit Out
Structure usually encompasses the building envelope.
Fit out usually encompases all interior finishes.
Doubling either one will raise o/a costs 1/6.
IN addition, we have never specified something like gold taps and where something like that is introduced by the client as a variation to the contract we have never charged extra for it.
Varying work defined on finished drawings, yes, that is a significant extra cost, but again, we seldom charge for such work - I cannot answer for most archtiects, but if its a more expensive house this is expected of the client and the increased fees covers it.
---------------------------------------
3. Dearer houses are seldom less complex than cheaper ones - the opposite is usually the case.
"Expensive" houses require larger spans, more complex structures, consequently difficult details and increased supervision and co-ordination to get it right.
To put this in a nutshell - an architect can leave a small builder to his own devices doing a 4M x 3M rear extension using traditional and standard details.
However a 6M x 6M extension with a bay window without pillars and a large lantern light in the centre of a flat roof immediately requires structural steel, increased cost and complexity and specialist detailing for the bay window.
The pro-rata cost and the percentage charge system in that case may not actually cover the cost increased workload and detailing, never mind the additional time on site doing limited inspections.
---------------------------------------
4. We never get the percentage we look for initially.
Architects usually charge fees on the cost per square foot for an building of a particular type.
Very often we will agree fees before starting work that may start out based on a percentage but that's merely to set the first figure that will be discounted.
We want the client to realise the value that's been achieved with the negotiation of fees.
---------------------------------------
5. The reverse can occur.
You can have your fees agreed and do a lot of work on detailnig and product research only to have the clients change their mind and reduce overall costs.
You've still gone and done the research and the detailing to finalise the cost, even though the client doesn't proceed with that work.
Happened on a project we did once where the granite walls - not promoted by us I hasten to add - after search in terms of materials pricing and finishing - were rejected as being too costly.
On another building a carefully detailed, proportioned and designed feature rooflight was scrapped.
On another a chandelier was introduced that requried a whole set of new supports, a winding mechanisms and control systems - we didn't charge additional fees for our time.
---------------------------------------
6. There are exceptions to every rule
Perhaps with some firms the percentage fees system has been abused, and I cannot defend every firm.
Most firms will agree discounts [you may have to haggle, but that's business - and expected].
In general the apparent increase in percentage-generated fees on more costly buildings is justified by the quality of work, detailing design and supervision requried for more expensive buildings.
The fees do not increase pro-rata but on a sliding scale - or did, when there was an RIAI scale fo fees to refer back to.
---------------------------------------
7. Bona Fides
I don't get paid for my posts here or the time I put into researching or composing my replies - none of the regular contributors or posters do.
You may not believe me until you've been on board with an architect on one of these projects and seen in through from start to finish, but take some solace from the fact that I've nothing to gain by lying to you.
ONQ.