i got letter re shankiel just last week. 2/3 beds. need to provide mortgage cert. all over again.
was it an offer or just update on info?
cheers.
Sorry it was just a request for mortgage cert. €205 for 2 bed, €230 for 3 bed. I'm sure this is just the beginning of the process. It will be another few months before we get to the squeaky bum stage.
CCC have been hounding my solicitor re. getting us to sign contracts and hand over monies as soon as possible. They have threatened to re-allocate our apt. if we do not finalise by April 26th...
We, and our solicitor, are in agreement that we will not be 'bullied' into signing before all property inspections are completed and meet with our approval...
Has anybody else received such treatment by the CCC?
One would think that they are giving us the apt. for free...just have to bite our collective tongues on this one...
Passat, i think our apartment is at the same stage as yours but we haven't heard a peep of the CCC. We handed our snag three weeks ago but have heard nothing from the builders or CCC yet.
CCC have been hounding my solicitor re. getting us to sign contracts and hand over monies as soon as possible. They have threatened to re-allocate our apt. if we do not finalise by April 26th...
We, and our solicitor, are in agreement that we will not be 'bullied' into signing before all property inspections are completed and meet with our approval...
Has anybody else received such treatment by the CCC?
One would think that they are giving us the apt. for free...just have to bite our collective tongues on this one...
Hi Passat, Yes ours is in that block too. I misinterpreted what you said earlier actually. We paid our deposit a few weeks back but our solicitor has assured us that although we've paid the deposit and signed papers, they are still obliged to complete the snag list to our satisfaction. Our snag list was huge so we will probably run into the same problems as yourselves. We haven't heard back to do the final inspection. Where do you go from here when you're not happy with what they've done? Did your engineer tell them that he/she wasn't happy with it or is it a case of take it or leave it with them?
Yip, that's about the size of it...we'll have to fight tooth and nail to ensure everything on the snag list is completed.
They just want the cash, once they have it, its our problem then...
Did you have any dampness problems?
Are you upstairs or on ground level?
We have serious dampness issues, the paint is peeling and there are loads of marks on the walls where they've tried to paint over. Is it the solicitor or engineer that fights our corner on the snags though?
We have serious dampness issues, the paint is peeling and there are loads of marks on the walls where they've tried to paint over. Is it the solicitor or engineer that fights our corner on the snags though?
No, not yet. Our engineer has it done in the report and is quesioning it but until the final snag we won't get an answer and i won't even hold my breath then.Do you know what is causing the dampness?
At the end of the day it is up to us, the buyer, to pursue them...
Engineer can only list the defects and recommend solutions...
Solicitor can only legally guide you...
I suppose it all depends on how tough you are willing to get!!!!