Just a warning to all of those who are contracting builders to carry out work.
Please Please Please try and understand the PC SUM & PROVISIONAL SUM issues that exist in Contracts. I have already this week had 4 calls from people in trouble financially in respect to increased costs on projects as a resut of increased prices from tender as a result of increases in the PC SUM and PROVISIONAL SUM alllowances that the Contractor allowed.
A PC SUM is an allowance made by an Architect or a builder in the price for a specialist contractor or specialist supplier. In most cases a PC SUM is allowed for electrics, plumbing, heating, kitchens, Windows etc etc. It is allowed on a lump sum provisional basis and the Client is responsible for the actual end cost of the item plus 5% for the Main contractor
It is in the Contractors interest in the tender process to keep this figure as low as possible as it makes his overall figure lower even if it is well known that the provisional cost is insufficient.
A Provisional Sum is similar but is for items that cannot be fully detailed or priced at the time of tender. Again the final price will be borne by the Client at the end of the day
It should be made aware to all Clients that these items need to be investigated in tenders and a like with like allowance should be made for all contractors in respect to these issues. A Clients representitive should always try and place a realistic value against these items in order to provent such movement throughout the currency of the Contract.
Sorry for the drawn out note but people should and need to be aware of the Contractual impact of PC and Provisional Sums
Please Please Please try and understand the PC SUM & PROVISIONAL SUM issues that exist in Contracts. I have already this week had 4 calls from people in trouble financially in respect to increased costs on projects as a resut of increased prices from tender as a result of increases in the PC SUM and PROVISIONAL SUM alllowances that the Contractor allowed.
A PC SUM is an allowance made by an Architect or a builder in the price for a specialist contractor or specialist supplier. In most cases a PC SUM is allowed for electrics, plumbing, heating, kitchens, Windows etc etc. It is allowed on a lump sum provisional basis and the Client is responsible for the actual end cost of the item plus 5% for the Main contractor
It is in the Contractors interest in the tender process to keep this figure as low as possible as it makes his overall figure lower even if it is well known that the provisional cost is insufficient.
A Provisional Sum is similar but is for items that cannot be fully detailed or priced at the time of tender. Again the final price will be borne by the Client at the end of the day
It should be made aware to all Clients that these items need to be investigated in tenders and a like with like allowance should be made for all contractors in respect to these issues. A Clients representitive should always try and place a realistic value against these items in order to provent such movement throughout the currency of the Contract.
Sorry for the drawn out note but people should and need to be aware of the Contractual impact of PC and Provisional Sums