- The builder requests the money
- Architect certifies the stage,
- Architect gives the stage cert to the solicitor
- The solicitor requested the money from the bank,
- The bank sends the cheque to the solicitor
- Solictor makes a cheque out to me, I lodge it in my account and I pay the
builders with a personal cheque