VintageTea2019
Registered User
- Messages
- 10
Just wondering what other people would do in this scenario, have no previous experience of dealing with builders or anything like this.
We signed a contract with a building firm in May 2019 for job that was estimated at 7 -9 weeks for completion. Not a massive job - small extension/knock together of existing kitchen and dining room to make open plan space and some related cosmetic improvements. So completion date aimed for 31st July. 7 staged payments outlined which we have paid 6/7 to date, paid in arrears as we went along following engineer check and satisfactory report. Final payment is/was due on completion of contract.
Initial work (demolition & structural work) carried out relatively quickly. Then delays started. Took forever to order kitchen and have fitted (in retrospect we should have used a separate company). Forever to order floor and have laid, lots of other similar delays and no apparent urgency to complete job etc etc.
Roll on to now, November. Final snag list completed by us back in end September. Lads showed up the week after, for 1 day, completed the major items on the snag list and there are still 5-10 non major items to complete (things like sockets to be correctly fitted to wall, some small replastering work etc.)
We still owe the final payment of about c€9k ( c€1k of which we would be disputing due to some additions that made necessary by builders carelessness while carrying out work). So say €8k due. Builder gone silent for past 3 weeks so our plan was to just hire a handiman to complete the final pieces and pay him from the amount we held due. Builder finally got back in touch this week to say they'll come back next week to finish the last bits.
At this point we are so fed up we almost want to just cut ties and don't allow them back and keep the funds they would be owed, as compensation for the delays and hassle caused to us during the whole process. They still have a key to the house (composite front door) which if we go that route we will have to have the lock changed as I'm not happy with a rogue key to our home being at large. This cost again funded by funds held back.
Any advice on dealing with this appreciated.
We signed a contract with a building firm in May 2019 for job that was estimated at 7 -9 weeks for completion. Not a massive job - small extension/knock together of existing kitchen and dining room to make open plan space and some related cosmetic improvements. So completion date aimed for 31st July. 7 staged payments outlined which we have paid 6/7 to date, paid in arrears as we went along following engineer check and satisfactory report. Final payment is/was due on completion of contract.
Initial work (demolition & structural work) carried out relatively quickly. Then delays started. Took forever to order kitchen and have fitted (in retrospect we should have used a separate company). Forever to order floor and have laid, lots of other similar delays and no apparent urgency to complete job etc etc.
Roll on to now, November. Final snag list completed by us back in end September. Lads showed up the week after, for 1 day, completed the major items on the snag list and there are still 5-10 non major items to complete (things like sockets to be correctly fitted to wall, some small replastering work etc.)
We still owe the final payment of about c€9k ( c€1k of which we would be disputing due to some additions that made necessary by builders carelessness while carrying out work). So say €8k due. Builder gone silent for past 3 weeks so our plan was to just hire a handiman to complete the final pieces and pay him from the amount we held due. Builder finally got back in touch this week to say they'll come back next week to finish the last bits.
At this point we are so fed up we almost want to just cut ties and don't allow them back and keep the funds they would be owed, as compensation for the delays and hassle caused to us during the whole process. They still have a key to the house (composite front door) which if we go that route we will have to have the lock changed as I'm not happy with a rogue key to our home being at large. This cost again funded by funds held back.
Any advice on dealing with this appreciated.