I hope someone can help me.
We recently started a self build and ordered 53 meters of cement for a raft foundation.
However 56 metres of concrete were delieverd to the site. We only used/needed 53 and the last lorry load had some left in it.
Do we have to pay for what 'wasn't used' ? My query been we only needed 53 meters, so will i just pay for that? When i rang my contact with the company for the exact figure to pay, he said refer to the delivery documents. Which tally's with 56 metres. Even though we only received/needed/ordered 53. It's a queston of 250 euro more if i have to pay the whole lot. Nolt much i know, but it could be used for something else plus its the principle of paying for something i didn't order.