Got a quote for €8500 to do the following in a 2800sq ft dormer new build;
All labour only:
Dry line inside of external walls with thermoboard - upstairs and down
Fit Rafterloc to roof pitch
Thermoboard over rafters
Slab ceiling upstairs and downstairs
Bridging of internal walls to ceilings as required.
The guy came recommended through another tradesman so probably a decent quote but probably a bit more than I expected (not that I'm an expert!).
He reckons, its about 2 weeks work for 5 men.
Does this look to be in roughly the right ballpark?
All labour only:
Dry line inside of external walls with thermoboard - upstairs and down
Fit Rafterloc to roof pitch
Thermoboard over rafters
Slab ceiling upstairs and downstairs
Bridging of internal walls to ceilings as required.
The guy came recommended through another tradesman so probably a decent quote but probably a bit more than I expected (not that I'm an expert!).
He reckons, its about 2 weeks work for 5 men.
Does this look to be in roughly the right ballpark?