Check out the last line though, that may slow it up but not by much
We can confirm the following in
> regard to the intended commencement dates for the various contracts for
> Line B1.
>
> Contract B1-100 - Ballyogan Road and Utility Contract - commencement
> date 26th February 2007, planned duration 13 months.
>
> Contract B1-160 - Minor Works - commencement date 26th February 2007,
> planned duration 4 months.
>
> Contract B1-300 - Structures - commencement date 5th March 2007, planned
> duration 16 months.
>
> Contract B1-400 - Railway Infrastructure - commencement date mid April
> 2007, planned duration 36 months.
>
>
> Please note the commencement date is the earliest date by which the
> contractor can commence works. The actual start date will generally
> depend on approval of traffic management.