Can someone advise me on the following spec that my architect has spec'd for my UFH and insulation. I don't think it is sufficient
Ground Floor
Slab to be in-situ reinforced concrete slab in accordance with the Structural
Engineers details, incorporating insulation to achieve min 0.25 W/sq mK.
75mm Cement: sand screed to accommodate Under floor heating pipes on
100mm high density insulation on 150mm in situ Concrete floor slab.
Dpc to be lapped and bonded with “Monarflex RMB” 400 Radon membrane on
hardcore. Radon sumps to be fitted with pipes from same to terminate outside
building and be capped.
25 mm “Kingspan” Therma Floor TF70 insulation to perimeter of slab taken up
between wall and slab. Ground floor construction to achieve minimum of 0.25 W/sq. mK
First Floor
Concrete panel floor slabs
To be 150mm precast concrete panel floor slabs in accordance with IS and
structural engineers specifications with 75mm Cement: sand screed to
accommodate Under floor heating pipes
Ground Floor
Slab to be in-situ reinforced concrete slab in accordance with the Structural
Engineers details, incorporating insulation to achieve min 0.25 W/sq mK.
75mm Cement: sand screed to accommodate Under floor heating pipes on
100mm high density insulation on 150mm in situ Concrete floor slab.
Dpc to be lapped and bonded with “Monarflex RMB” 400 Radon membrane on
hardcore. Radon sumps to be fitted with pipes from same to terminate outside
building and be capped.
25 mm “Kingspan” Therma Floor TF70 insulation to perimeter of slab taken up
between wall and slab. Ground floor construction to achieve minimum of 0.25 W/sq. mK
First Floor
Concrete panel floor slabs
To be 150mm precast concrete panel floor slabs in accordance with IS and
structural engineers specifications with 75mm Cement: sand screed to
accommodate Under floor heating pipes