So there is 6.5K remaining and to finish it would cost 10K. Easiest solution is to clarify with the builder that he is not coming back and finish the job by paying out the 10K to someone else. Basically he's got most of his money and 6.5K on 10K of work isn't worth his time. Next time keep back 20K for the 10K remaining work and you'll be amazed at how quick a builder is to show up.
Just not right that the builder can just walk away, got his profit and if completing job it eats into profit
I don't know how how much 3.5 K is in the scheme of a build but it wouldn't be much on an extension job that you said was quoted low so I don't think we're talking massive profits. If your friend is happy with the work so far, well another 3.5K is a small price to pay. Your friend made the mistake in paying up front.
Builder's profit is long since spent and forgotton about.
feltox,
What size was the extension approximately and what kind of work was done to the house?
ONQ.
roof of house taken off, put in second floor 5 bedrooms and toilet, new roof and move out kitchen downstairs
roof of house taken off, put in second floor 5 bedrooms and toilet, new roof and move out kitchen downstairs
When you say second floor, do you mean this was originally a bungalow and they made it into a two storey house, with a new 1st floor, walls, ceiling and roof over that?
ONQ.
We use cookies and similar technologies for the following purposes:
Do you accept cookies and these technologies?
We use cookies and similar technologies for the following purposes:
Do you accept cookies and these technologies?