A relation of mine is having trouble getting a builder to come back and finish last bit of works/snags on an extension eg footpaths, small bit of drainage, shower doors, bits of internal work, site clearance etc. The reason to go with the builder was the good price at time.
main points
1. got a builder to do a extension to house.
2. verbally agreed price.
3. no contract signed.
4. job went way over time
5. about 6.5k of money left to finish(willing to pay builder if he comes back and does Job) but cant wait much longer as he has being on site only one day since 01/01/10
6. builder looks have no intention of finishing.
From what i hear he has started an extension now on another person house so he cant claim he does not have money. He avoids my relation calls and I think they feel initimated by him as he is nice to husband and verbally abuses wife when husband not on site
From what i see he underpriced the job first day
what do you do?
1.any way to force builder to come back?
2.If 10k of work to put right can you go after builder for shortfall to put his work right.
3.How do you draw a line in sand with builder if he does not come back, you finish job yourself what is stopping builder coming back in a year looking to do work and get money
4. Could you picket his new site, I would be certain a builder would not want a adult and a few kids with signs 'why doing you finish jobs'
to me it looks like they will have to finish job themselves as no contract, and put in down to bad experience
The person is a relative and I dont like to see people in general being ripped off.
thank you
main points
1. got a builder to do a extension to house.
2. verbally agreed price.
3. no contract signed.
4. job went way over time
5. about 6.5k of money left to finish(willing to pay builder if he comes back and does Job) but cant wait much longer as he has being on site only one day since 01/01/10
6. builder looks have no intention of finishing.
From what i hear he has started an extension now on another person house so he cant claim he does not have money. He avoids my relation calls and I think they feel initimated by him as he is nice to husband and verbally abuses wife when husband not on site
From what i see he underpriced the job first day
what do you do?
1.any way to force builder to come back?
2.If 10k of work to put right can you go after builder for shortfall to put his work right.
3.How do you draw a line in sand with builder if he does not come back, you finish job yourself what is stopping builder coming back in a year looking to do work and get money
4. Could you picket his new site, I would be certain a builder would not want a adult and a few kids with signs 'why doing you finish jobs'
to me it looks like they will have to finish job themselves as no contract, and put in down to bad experience
The person is a relative and I dont like to see people in general being ripped off.
thank you