Hi,
Making progress through our self-build.
And, it really is a self build, thus far the only contractor we have employed was a guy fitting the solar panels (half a days work). Foundations, stick built timber frame, slates etc have all been completed by the site owners.
We have contracted out the external plastering, which was due to start last week and would have taken a few days to complete. Within a few hours of the plasters arriving on site.
A lady from the HSA made a visit! said she was passing by and decided to call in. Asked to see our canteen facilities etc. and inspected our scaffolding.
There was a ladder access to the scaffolding and one or two planks missing, and we have no canteen facilities, so work was called to a halt and a warning issued.
I accept that our scaffolding wasn't to text book standards so we have rectified, this is not a problem.
My question is, do we need to supply canteen facilities for work that will be completed in 3-4 days on a one off house?
And can the HSA just "Pop in" whenever they like?
What if it was just the owners on site?
Advice /opinions appreciated!
Making progress through our self-build.
And, it really is a self build, thus far the only contractor we have employed was a guy fitting the solar panels (half a days work). Foundations, stick built timber frame, slates etc have all been completed by the site owners.
We have contracted out the external plastering, which was due to start last week and would have taken a few days to complete. Within a few hours of the plasters arriving on site.
A lady from the HSA made a visit! said she was passing by and decided to call in. Asked to see our canteen facilities etc. and inspected our scaffolding.
There was a ladder access to the scaffolding and one or two planks missing, and we have no canteen facilities, so work was called to a halt and a warning issued.
I accept that our scaffolding wasn't to text book standards so we have rectified, this is not a problem.
My question is, do we need to supply canteen facilities for work that will be completed in 3-4 days on a one off house?
And can the HSA just "Pop in" whenever they like?
What if it was just the owners on site?
Advice /opinions appreciated!