Hi,
The external plastering has been done on our new build so its time to start doing internal work. We are getting the chasing done early next week but I am confused as to the order of events thereafter. I assumed internal plastering had to wait until electrics/plumbing/screed done but I am told otherwise. So can someone put it in order for me and include any tasks I haven't got. Its a block build with bead cavity insulation. No dry-lining.
1. Chasing
2. Electric Wiring (first fix?)
3. Fill back of windows with insultion and cememt and install Window Boards
4. Internal Plastering
5. Put down floor insulation
6. Plumbing (first fix?)
7. Screed flooring
8. Stairs & Doors and other carpentry work
9. Kitchen & Toilets
10. Electrics (second fix)
11. Plumbing (second fix)
Thanks in advance.
The external plastering has been done on our new build so its time to start doing internal work. We are getting the chasing done early next week but I am confused as to the order of events thereafter. I assumed internal plastering had to wait until electrics/plumbing/screed done but I am told otherwise. So can someone put it in order for me and include any tasks I haven't got. Its a block build with bead cavity insulation. No dry-lining.
1. Chasing
2. Electric Wiring (first fix?)
3. Fill back of windows with insultion and cememt and install Window Boards
4. Internal Plastering
5. Put down floor insulation
6. Plumbing (first fix?)
7. Screed flooring
8. Stairs & Doors and other carpentry work
9. Kitchen & Toilets
10. Electrics (second fix)
11. Plumbing (second fix)
Thanks in advance.