Hi,
I am currently at roofing stage on a direct labour new build. What is the sequence of events once the felt goes on ?
Is it :
Slates
Plaster chimney
Soffit/Facia (?) - does this include downpipes ?
External plastering upstairs
Drop scaffolding a level
External plastering downstairs
Windows
Am I missing anything or is it wrong order ?