Comments/Advice sought on Quote
I have received my first quote back for the construction of a TF 2600 sq ft dormer in the West. It is much more than I had mentally been budgeting and whilst it is high spec and designed to get a very high BER rating I am wondering if there are ways I might still achieve a high BER but at a lower cost. I would like to get people's feedback on some elements of the quote which I will list to see if people feel that these are expensive/overpriced.
The total cost including everything except sanitary ware and kitchen units is approx. €350,000 ex. VAT.
Some elements of the quote:
Preliminaries €26000 - includes Site supervision, Site Accommodation, Teleporter Hire, Insurance (€3600), Power, Scaffolding etc.
Insulation €21500 Rockwool and Xtratherm
External Plastering €15000
Internal Dry Lining/Plastering €32000
Windows/External Doors Alu-Clad (approx 30) €35000
Electrical €8500
Condensing Boiler, Underfloor Heating, Solar Panels €31000
Comments very welcome
I have received my first quote back for the construction of a TF 2600 sq ft dormer in the West. It is much more than I had mentally been budgeting and whilst it is high spec and designed to get a very high BER rating I am wondering if there are ways I might still achieve a high BER but at a lower cost. I would like to get people's feedback on some elements of the quote which I will list to see if people feel that these are expensive/overpriced.
The total cost including everything except sanitary ware and kitchen units is approx. €350,000 ex. VAT.
Some elements of the quote:
Preliminaries €26000 - includes Site supervision, Site Accommodation, Teleporter Hire, Insurance (€3600), Power, Scaffolding etc.
Insulation €21500 Rockwool and Xtratherm
External Plastering €15000
Internal Dry Lining/Plastering €32000
Windows/External Doors Alu-Clad (approx 30) €35000
Electrical €8500
Condensing Boiler, Underfloor Heating, Solar Panels €31000
Comments very welcome