Hi Sandylab
My property management company are looking after apartments in Sun Palace.
Phase 1 is completed while amenities are still not available. I was told residnets will have a chance to take extra services in the site once phase 2 was handed over. But Phase 2 will not have been completed by sooner than the Spring 2008. Further to that, there are no shops or restaurants on the ground floor in Phase 1. Delays are due to a conflict between developer and constructor. Phase 2 has been constructed since September 2006, actually.
This is the main reason why you may have difficulties in finding a tenant. However, our studio apartment in Tower H at 6th floor with garden view was rented for HUF100,000 with 12 months lease. The apartment was occupied in 1 week when fitout was done.
For further information feel free to contact me