We are currently identifying blocklayers for our new build, and we are wondering what the norm is with regards to pricing... is it more normal to be charged a price per block, or to be charged a price per day?
As I see it, as I will be buying the blocks, I will know exactly how many blocks have gone into the build and thus will know exactly how much I should be charged. Whereas, with a charge-per-day agreement, I believe there is room for me to be ripped off, as I work fulltime and will not always be around on the site to see whether the builders have put in full days or not.
Am I correct in thinking that the price per block is a "safer" method to agree to?
I'd like to hear opinions from others regarding the pros and cons of both pricing methods.
thanks,
We are currently identifying blocklayers for our new build, and we are wondering what the norm is with regards to pricing... is it more normal to be charged a price per block, or to be charged a price per day?
As I see it, as I will be buying the blocks, I will know exactly how many blocks have gone into the build and thus will know exactly how much I should be charged. Whereas, with a charge-per-day agreement, I believe there is room for me to be ripped off, as I work fulltime and will not always be around on the site to see whether the builders have put in full days or not.
Am I correct in thinking that the price per block is a "safer" method to agree to?
I'd like to hear opinions from others regarding the pros and cons of both pricing methods.
thanks,
Has anyone heard of blocklayers charging "by the block"...but working through the windows/opes?
We use cookies and similar technologies for the following purposes:
Do you accept cookies and these technologies?
We use cookies and similar technologies for the following purposes:
Do you accept cookies and these technologies?