Hi Dusty - Thanks a million for the reply.
You're right about the external leave as such - Not too worried about that as such.
Can you advise on the following.
when he fills and blinds, and as you say layes radon barrier as one across the whole internal space, will he only do it up to the level of the top of block 2 ? see example below
is block 3 layed ontop of insulation board, ontop of few inches of filling, or is it layed on the radon barrier, on block 2 ?
...............| Block 3
...............- Radon Barrier
filling........| Block 2 (internal)
filling........| Block 1 (internal)
I just don't understand where the insulation board and concrete comes into it ?
I'm afraid that I'll end up with the internal walls built on 4 inches on contrete, on 4 inches of Aeroboard, on a few inches of filler, on the 2 internal blocks.
To me this seems wrong for load bearing walls. Surely there should be no weight on the aeroboard ?
I've bought that book - but it's a bit difficult to follow if you're not in the trade.. Must have another gander...
Thanks again Dusty,
Furious D.